The project management plan states a predictive development approach for the project deliverables. The project manager is now developing a schedule for the project, since the development of the Scope Baseline is nearly done. At which phases of the project, the stakeholders influence on the project is maximum?
Explanation:
How does an agile project account for risks and uncertainties?
Explanation:
What is an incremental development approach?
Explanation:
In an incremental development approach the deliverable is not developed and validated as a whole at the end of the project, but developed and delivered successively ithroughtout the project. This parts of the deliverable are also called increments.
In an agile project the next iteration planning is scheduled for the upcoming week. What does this typically mean?
Explanation:
In an agile project the work is planned by the project team in an iteration planning at the beginning of every sprint / project iteration.
You are project manager in a large construction project. The planning is nearly done and now the detailed plans are presented to the team and important stakeholders. How is this kind of meeting called?
Explanation:
A kick-off meeting is scheduled to inform the stakeholders on the project and the project plan.
As a project manager of a new IT project you determine the development approach for the project. What is meant by the term \\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\"increment\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\" in an agile environment?
Explanation:
Increments are parts of the deliverable, which are successively devloped throughout an agile project life cycle. They are defined as finished parts of the deliverable, which are ready to the release to the client.
A company is considering two projects for the upcoming fiscal year. Taking the potential costs and profit into account, a ROI is calculated for both projects. For project 1 the ROI is 5,5 Mio USD and for project 2 the ROI is calculated at 6,25 Mio USD. If project 1 is chosen, what will the opportunity costs be?
Explanation:
Opportunity costs are defined as a loss of other alternatives when one alternative is chosen. Since project 1 is chosen, the ROI (or profit) of project 2 will be the opportunity costs (6,25 Mio USD)
As part of the initiation of the project, a project charter is developed. What is typically not part of the project charter in an agile environment?
Explanation:
A detailed description of risks as a result of a thorough risk analysis is typically not necessary for the initiation and approval of the project.
In an predictive project environment a detailed project management plan developed to organize the execution of the project. Incorporating risks and uncertainties into the plan is a critical part of the planning. What is least likely going to happen, when the project team tries to account for unknowable-unknowns?
Explanation:
Unknowable-unknowns are risks or potential threat that are not known and cannot be quantified or controlled. Gathering information and closely monitoring risks through the entire project is a good way to cover those risks, identifying them as early as possible, and trying to incorporate them into the plan or react as they occur.
A kick-off meeting is part of many projects. In a kick-off the project and the project plan is presented to the team and important stakeholders. What is not true about project kick-off meetings?
Explanation:
The kick-off meeting\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\'s purpose is to present informationen on the project and the project plan to a wider audience (e.g., the team and other important stakeholders). It is not the purpose of a kick-off to facilitate or even escalate conflicts of interest among the stakeholders.
A RACI matrix is used to define responsibilities in a project. What is not shown in a RACI matrix?
Explanation:
Whether or not a work packages has sufficient resources in order to execute the work, is not shown in RACI matrix. It only shows the resources doing the work, accountabilities, and persons, who contribute or need to be informed.
What is the main difference between a backlog and a scope statement (as part of the scope baseline)?
Explanation:
In an agile project a backlog is used to constantly developed and reprioritize the scope of a project. The product owner has the responsibility over the backlog and works continuously with the client, the team, and other stakeholders to update and refine the backlog as new information becomes available. A change request procedure is typically needed in order to change the approved and fixed project scope statement.
You are project manager in a large contruction project. Changes in a project are nearly inevitable. According to the change management procedures, changes are documented in the project management plan. These changes have been distributed and published to the stakeholder as stated in the communication management plan. Some stakeholders are surprised of the changes, since they have not been notified. What should the project manager do.
Explanation:
Since the changes are distributed and published to the stakeholders, the situation indicates that some information procedures in the communication management plan are not working properly. To prevent this prolems in the future, the best course of actions is to prevent this situations in the future by reviewing (and if necessary changing) the communication management plan.
The Fishbone diagram is a helpful tool to quickly identify root causes of a problem for further investigation. What is not true about a Fishbone diagram?
Explanation:
A quantitative assessment of the root causes is typically not part of a Fishbone diagram.
Control charts help to determine if the results of a process are within acceptable limits. It gives you an overview on the stability of a process. What is a general rule, when interpreting the results of a control chart?
Explanation:
The rule of seven states that the process is out of control, if seven consecutive points are on one side of the mean, although none of these points are outside of the control limits.
You are planning a new project. To accounts for uncertainties the project manager develops a risk register, in which risks are documented and analyzed. What is typically not part of a risk assessment?
Explanation:
The budgeting of risk is typically not part of a risk assessment. It is relevant to determine how to handle the risks and account for the uncertainties in the project management plan, but they are not part of the risk assessment.
The Dreyfus Model of adult skill acquistion shows five different stages for learning a new skill. In which stage are decision more based on a intuitive understanding than on a analytic analysis of the situation?
Explanation:
To make the decision intuitively a deep knowledge and understanding is necessary. An expert encompasses the most knowledge and understanding, so that his decision are more likely to be based on intuition.
Why should quality be planned in rather than be inspected in?
Explanation:
Preventing defects is often less costly than correcting defects. Following this statement when planning quality management, results in an improved quality and is less costly.
accounting for the information needs of stakeholders is a crucial part for a successful stakeholder management. As a project manager in a project you have identified several different groups of stakeholder with different requirements on the communication. When should you use a milstone chart instead of a bar chart?
Explanation:
A milestone chart is often used, when you want to communicate the progress in a less detailed way. Since the team is interested in this details, a bar chart would be a good way to present the progress to the team. For senior management ofte less details are required, therefore a milestone chart is the best way to communicate the progress to the senior management.
When planning the budget for a project, the project manager takes differnt types of cost into account. What is not part of the project\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\'s budget?
Explanation:
Opportunity costs are defined as a loss of other alternatives when one alternative is chosen. They are used for calculation and decision making, but they are not costs that occur and they are not part of a project\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\'s budget.
The project charter is the initiation document of a project. In many organizations the project charter is signed by the people involved in the project. Which signature is least likely to be found on a project charter?
Explanation:
Team members typically do not decide and approve on projects. Therefore, they do not sign the project charter.
Project are often part of a matrix-organisation, in which the project uses resources (e.g., team members) that are assigned to a functional department. Therefore, projects rely on the support of the performing organisation. What is the best way for a project to obtain the support necessary?
Explanation:
Connecting the personal needs of a sponsor to a project, does not necessarily result in a wider support within the organization. A communication plan and a team management plan are also not necessarily ensuring that the organization provides the support that is needed for the project. To gain support the best course of action is to align the goals of the project with the strategic business goals of the organization.
The communication management plan formalizes communication throughout the project. It defines meeting structures and frequency, reporting structures, and which communication technology should be used. Which of the following examples of communication technologies has the highest density of information?
Explanation:
An interactive meeting has the highest density of informationen.
What is true about time-boxing?
Explanation:
Agile project use the time-boxing approach is mainly used in agile project for nearly every aspect of the project. Meetings are timeboxed (e.g., the daily stand-up), but project phases are also time-boxed. This is to prevent projects from failing, when you cannot rely on an extensive planning due to the lack of information needed to plan the project in the first place. In a time-box the schedule and budget is fixed, rather than the desired outcome.
In a plan-driven projects estimations are a crucial part when planning the project. What is not a form of deterministic estimating?
Explanation:
Deterministic estimating techniques use a single number value for an estimate. A range estimate on the other hand relies on several values that determine the estimated range and is therefore not a deterministic estimating technique.
What is the difference between precision and accuracy?
Explanation:
Accuracy means how close a given set of measurements (observations or readings) are to their true value, while precision show how close or dispersed the measurements are to each other.
What is not a Kanban principle?
Explanation:
Visualizing the work flow, limiting work in progress, and managing the flow of work are essential Kanban principles. Correcting defects is not a Kanban principle.
In an agile proect management the teamboard is essential for managing the work among the team member. What is not a rule for a teamboard meeting?
Explanation:
The time-box approach ensures that teamboard meeting are not delayed. Everybody on the team should present an overview an the work that needs to be done, the progress made, and the obstacles and challanges they are facing. But the teamboard meeting is not a meeting for detailed discussion. If issues arises and a lengthy and detailed discussion is necessary, an additional meeting is set up.
you are project manager of a large contruction project. A new central warehouse shoud be built for the company. In the middle of execution you discover, that the initial timeline cannot be met. More time is needed in order to complete the project. What is the best course of action?
Explanation:
Reducing the scoipe (if even possible) affects the satisfaction of the stakeholders in a negative way. Therefore, it is not the best action. Demanding overtime is expensive and not necessary, if other options are available. Before you meet with the senior management you should determine options for schedule compression. This would have the least negative impact on the project.
You are managing a project in a manufacturing company. The project is plan-driven and you used the schedule network analysis to develop the schedule. The project is now in the middle of execution. The CPI for the project is at 0,92 and the SPI is at 0,79. What has probably happened?
Explanation:
Based on the CPI and SPI the project is over budget and behind schedule. A scope change does not necessarily result in cost overruns and delays. An unexpected purchase could explain the cost overrun but not necessarily the delay of the schedule. There is no evidence that an agile approach would have lead to a better project management. It is likely that an activity on the critical path needed more resources and took longer. This explains the cost overruns and the delay.
You are project manager of a small process improvement project, that just got approved and initiated. Now you start the planning of the project. You are approached by a stakeholder, who asks you about the project\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\'s budget and the cost baseline. What should you answer?
Explanation:
The project charter shows the initial budget for a project, but does not show any detailed cost estimations (which are part of the cost baseline). Rough estimates are noch detailed enough or create a false impression on the project\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\'s estimated costs, so it is not wise to communicate estimates among stakeholders. You can determine a budget without cost estimations, but it is also not wise to do so. To give the stakeholder the information he requested, you need to finish the cost baseline as part of the planning processes.
A project\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\'s budget at completion (BAC) is at 200.000€. The team completed 35% of the work and you spent 75.000€ on this work packages for the resources to complete those work packages. Evaluate the situation.
Explanation:
Based on the given situation, the project manager cannot assess the progress on the schedule, but she can draw conclusions for the budget. The cost variance is at -5.000€ and the project needs additional funds, which needs to requested via a change request. There is no general rule or indication in the situation, that minor changes do not need to be requested by a change request. Based on the given situation you can only say, that project has overrun its costs by 5.000€ and it needs additional funding.
Wich of the following statements describes the term \\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\"quality\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\" best?
Explanation:
Quality is defined as the degree to which the project\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\'s meets the deliverables.
You are project manager working on an agile project to develop a new IT solution for a customer. You work with the stakholders to figure out, what requirements the IT solution should meet. What is the best tool to develop and document the requirements in this situation?
Explanation:
A user story is an informal, general explanation of a software feature written from the perspective of the end user or customer. The other tools are no specific tools to determine and document requirements.
What is not part of a value stream map?
Explanation:
A value stram map shows the process steps and activities as well as their connections. A swimlane is often the basis for the value stream map. In addition to the process steps the flow of information and the used technologies are also depicted alongside the process as well as different KPIs. The work in progress alongside the process is least likely to be a part of the value stream map.
You are project and the last report indicates, that the project has overrun ist initial budgeted costs. You can see this, because…
Explanation:
A CPI lower than 1 indicates that the Actual Cost for the project are higher than the Earned Value (which is the work done expressed in planned costs). Therefore, you can conclude that a project has overrun ist costs, if the CPI is lower than 1.
What is the standard deviation?
Explanation:
The standard deviation is defined as the measurement of a range around the mean.
KPIs are used to monitor and evaluate the project\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\'s progress. What is not a characteristic of a good KPI according the SMART principles?
Explanation:
According to the SMART principles KPIs should be specific, meaningful, achievable, relevant, and timely.
You are project manager in a plan-driven project. Right now you are developing the schedule based on the estimates you have made with your project team. You are using the schedule network analysis to determine the critical path. What does a free float of 6 days for an activity indicate?
Explanation:
A free float is the amount of time an activity can be delayed without delaying ist successor activity while sill adhering to any imposed schedule constraints. Therefore, it says nothing about any delays of predecessor activities and a delay on the project end date. Just based on the free float you cannot assume that the activity is on the critical path.
What is meant by a waterfall approach in project management?
Explanation:
A waterfall approach is another term for a strictly sequential relationship of project phases, where a phase can only start of the predecessor is finished.
You are project manager in a contruction project, where an existing oil pipeline should be extended. You are facing a vast stakeholder landscape with many different economic, social, and ecological standpoints and interests. Before you start planning the project, you work with your sponsor to determine, whose interest should be taken into account. What is the best tool, that might help you in this situation?
Explanation:
Since you are facing many different stakeholders with different opinions and interests, you need structure and prioritize the stakeholder. By using a power-interest-grid the project manager and his sponsor are able to structure the vast stakeholder landscape by the interest a stakeholder shows on the project and the potential the stakeholder has over the project. Engagement strategies (e.g., using questionaires and surveys) can later be developd based on the prioritization in the stakeholder grid.
The BAC for a project is 400.000 USD. The project is about 40% done and for the most time the work was executed as planned. Only a new machine had to be bought. The additional costs of 20.000 USD were not part of the initally planned budget. What is the current CPI of the project?
Explanation:
EV = 400.000 x 0,4 = 160.000 AC = 160.000 (work was executed as planned) + 20.000 (additional costs occured up to this point in time) = 180.000 CPI = EV/AC = 160.000/180.000 = 0,89
You are assigned as a project manager to a new project. The project is in the middle of execution. At first you want to take a look on the requirements, how the are implemented in the work packages, and what the status on the fulfillment of the requirements is. Which document should you read?
Explanation:
The Project Scope Statement (and by extension the Scope Baseline) contains the fixed and approved requirements for the project. The requirements documentation is mainly a list thats supports the process of gathering requirements with stakeholders until the Scope Baseline is fixed. Additionally, the requirements documentation contains no information on the status of the requirements. The requirements and information on the status s over the entire course of the project are documented in the requirements traceability matrix.
You are project manager in an IT project. The last quality reports indicates that the recently developed IT solution still has some bugs. These bugs need to be fixed to get the deliverables approved by the client. You evaluate that the additional work to fix the bugs will cost the project 10.000 USD. What are these costs called?
Explanation:
The situation describes non-conformance costs or failure costs. Since the bugs need to be corrected before the deliverable are accepted, they are project-internal failure or non-conformance costs.
You are project manager in a project that is nearly done. So far the project went well. Most of the work packages got finished on time and budget. For the remaining work packages you still have a financial reserve of 10.000 USD. You discuss the remaining work with your team and they state, that the work packages need addtional funding of 15.000 USD to get the done properly. You decide to issue a change request to get the funding the project team needs for the remaining work packages. How much additional budget will you request from your sponsor?
Explanation:
Since the project still has a financial reserve for the remaining work of 10.000 USD, the project needs 5.000 USD additional funding.
Over the course of project stakeholder will influence the project on some level or another. This influence varies over time. During which stage of the project the stakeholder\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\'s influence is maximum?
Explanation:
The influence of the stakeholder is higher at the beginning of the project and decreases over time as the projects gets work and results done.
What is typically not part of a business case?
Explanation:
How rssources will released from a project is typically defined in the resource management plan of a project. Overall guidelines for project management might influence and define this process, but those information are not part of business case. In general, a business answers the question, why project are undertaken by an organization, how the contribute the busiess strategy, and what strategic goals need to be achieved.
You are project manager assigned to a new project. The planning of the project is done and the work on the deliverables has started. You want to understand, what role and responsibility the different team members have. Where should you look for this information?
Explanation:
The Resource Management Plan provides information on the roles and responsibilities of different project members. It often includes an organizationals breakdown structure or some form of responsibility assignment matrix. The team charter encompasses values and guidelines for the team, but no information on individual roles and responsibilities.
Earned Value Management includes formulas for forecasting based on the given situation in a project. The Estimate at Completion (EAC) is such a forecasting indicator. What is typically not included in the calculation of the EAC?
Explanation:
The Variance at Completion is the difference betwenn the BAC and EAC. The formula for the EAC might include BAC, CPI, and SPI, depending on the situation and what formula you want to use for forecasting.
You are project manager of the project, that implements a new production process in an engineering company. The process is intended to produce steel bolts with a length of 30 cm. The control limits are 29.955cm and 30.045cm. The measurements made at the end of the test run yielded the following results: 30.033cm, 29.982cm, 29.995cm, 30.006cm, 29.970cm, 29.968cm, 29.963cm, 29.958cm, 29.962cm, 29.979cm, 29.959cm. What should the project conclude from this measurements?
Explanation:
The rule of seven is violated, since seven consecustive points are below the mean. The cause for this behaviour should be further investigated, even if the control limits are not violated.
Quiz Complete!
Your Score: 0/50
Percentage: 0%
What is an incremental development approach?
Explanation:
In an incremental development approach the deliverable is not developed and validated as a whole at the end of the project but developed and delivered successively throughout the project. These parts of the deliverable are also called increments.
In an agile project the next iteration planning is scheduled for the upcoming week. What does this typically mean?
Explanation:
In an agile project the work is planned by the project team in an iteration planning at the beginning of every sprint / project iteration.
You are project manager in a large construction project. The planning is nearly done and now the detailed plans are presented to the team and important stakeholders. How is this kind of meeting called?
Explanation:
A kick-off meeting is scheduled to inform the stakeholders on the project and the project plan.
As a project manager of a new IT project you determine the development approach for the project. What is meant by the term "increment" in an agile environment?
Explanation:
Increments are parts of the deliverable which are successively developed throughout an agile project life cycle. They are defined as finished parts of the deliverable which are ready for release to the client.
A company is considering two projects for the upcoming fiscal year. Taking the potential costs and profit into account a ROI is calculated for both projects. For project 1 the ROI is 5.5 Mio USD and for project 2 the ROI is calculated at 6.25 Mio USD. If project 1 is chosen what will the opportunity costs be?
Explanation:
Opportunity costs are defined as a loss of other alternatives when one alternative is chosen. Since project 1 is chosen the ROI (or profit) of project 2 will be the opportunity costs (6.25 Mio USD).
As part of the initiation of the project a project charter is developed. What is typically not part of the project charter in an agile environment?
Explanation:
A detailed description of risks as a result of a thorough risk analysis is typically not necessary for the initiation and approval of the project.
In a predictive project environment a detailed project management plan is developed to organize the execution of the project. Incorporating risks and uncertainties into the plan is a critical part of the planning. What is least likely going to happen when the project team tries to account for unknowable-unknowns?
Explanation:
Unknowable-unknowns are risks or potential threats that are not known and cannot be quantified or controlled. Gathering information and closely monitoring risks through the entire project is a good way to cover those risks identifying them as early as possible and trying to incorporate them into the plan or react as they occur.
A kick-off meeting is part of many projects. In a kick-off the project and the project plan is presented to the team and important stakeholders. What is not true about project kick-off meetings?
Explanation:
The kick-off meeting's purpose is to present information on the project and the project plan to a wider audience (e.g. the team and other important stakeholders). It is not the purpose of a kick-off to facilitate or even escalate conflicts of interest among the stakeholders.
A RACI matrix is used to define responsibilities in a project. What is not shown in a RACI matrix?
Explanation:
Whether or not a work package has sufficient resources in order to execute the work is not shown in a RACI matrix. It only shows the resources doing the work accountabilities and persons who contribute or need to be informed.
What is the main difference between a backlog and a scope statement (as part of the scope baseline)?
Explanation:
In an agile project a backlog is used to constantly develop and reprioritize the scope of a project. The product owner has the responsibility over the backlog and works continuously with the client the team and other stakeholders to update and refine the backlog as new information becomes available. A change request procedure is typically needed in order to change the approved and fixed project scope statement.
You are project manager in a large contruction project. Changes in a project are nearly inevitable. According to the change management procedures, changes are documented in the project management plan. These changes have been distributed and published to the stakeholder as stated in the communication management plan. Some stakeholders are surprised of the changes, since they have not been notified. What should the project manager do.
Explanation:
Since the changes are distributed and published to the stakeholders, the situation indicates that some information procedures in the communication management plan are not working properly. To prevent this problems in the future by reviewing (and if necessary changing) the communication management plan.
The Fishbone diagram is a helpful tool to quickly identify root causes of a problem for further investigation. What is not true about a Fishbone diagram?
Explanation:
A quantitative assessment of the root causes is typically not part of a Fishbone diagram.
Control charts help to determine if the results of a process are within acceptable limits. It gives you an overview on the stability of a process. What is a general rule, when interpreting the results of a control chart?
Explanation:
The rule of seven states that the process is out of control, if seven consecutive points are on one side of the mean, although none of these points are outside of the control limits.
Why should quality be planned in rather than be inspected in?
Explanation:
Preventing defects is often less costly than correcting defects. Following this statement when planning quality management, results in an improved quality and is less costly.
You are planning a new project. To account for uncertainties the project manager develops a risk register, in which risks are documented and analyzed. What is typically not part of a risk assessment?
Explanation:
The budgeting of risk is typically not part of a risk assessment. It is relevant to determine how to handle the risks and account for the uncertainties in the project management plan, but they are not part of the risk assessment.
The Dreyfus Model of adult skill acquistion shows five different stages for learning a new skill. In which stage are decision more based on a intuitive understanding than on a analytic analysis of the situation?
Explanation:
To make the decision intuitively a deep knowledge and understanding is necessary. An expert encompasses the most knowledge and understanding, so that his or hers decision are more likely to be based on intuition.
Accounting for the information needs of stakeholders is a crucial part for a successful stakeholder management. As a project manager in a project you have identified several different groups of stakeholder with different requirements on the communication. When should you use a milstone chart instead of a bar chart?
Explanation:
A milestone chart is often used, when you want to communicate the progress in a less detailed way. Since the team is interested in this details, a bar chart would be a good way to present the progress to the team. For senior management often less details are required, therefore a milestone chart is the best way to communicate the progress to the senior management.
When planning the budget for a project, the project manager takes different types of costs into account. What is not part of the project's budget?
Explanation:
Opportunity costs are defined as a loss of other alternatives when one alternative is chosen. They are used for calculation and decision making, but they are not costs that occur and they are not part of a project's budget.
The project charter is the initiation document of a project. In many organizations the project charter is signed by the people involved in the project. Which signature is least likely to be found on a project charter?
Explanation:
Team members typically do not decide and approve on projects. Therefore, they do not sign the project charter.
Projects are often part of a matrix-organisation, in which the project uses resources (e.g., team members) that are assigned to a functional department. Therefore, projects rely on the support of the performing organisation. What is the best way for a project to obtain the support necessary?
Explanation:
Connecting the personal needs of a sponsor to a project, does not necessarily result in a wider support within the organization. A communication plan and a team management plan are also not necessarily ensuring that the organization provides the support that is needed for the project. To gain support the best course of action is to align the goals of the project with the strategic business goals of the organization.
The communication management plan formalizes communication throughout the project. It defines meeting structures and frequency, reporting structures, and which communication technology should be used. Which of the following examples of communication technologies has the highest density of information?
Explanation:
An interactive meeting has the highest density of informationen.
What is true about time-boxing?
Explanation:
Agile project use the time-boxing approach in many aspects of the project. For example, meetings are timeboxed (e.g., the daily stand-up), but project phases are also time-boxed (in a time-box the schedule and budget is fixed, rather than the desired outcome).
In a plan-driven projects estimations are a crucial part when planning the project. What is not a form of deterministic estimating?
Explanation:
Deterministic estimating techniques use a single number value for an estimate. A range estimate on the other hand relies on several values that determine the estimated range and is therefore not a deterministic estimating technique.
What is the difference between precision and accuracy?
Explanation:
Accuracy means how close a given set of measurements (observations or readings) are to their true value, while precision show how close or dispersed the measurements are to each other.
What is not a Kanban principle?
Explanation:
Visualizing the work flow, limiting work in progress, and managing the flow of work are essential Kanban principles. Correcting defects is maybe a principle but has no connection to the Kanban principles.
In an agile project management the teamboard is essential for managing the work among the team members. What is not a rule for a teamboard meeting?
Explanation:
The time-box approach ensures that teamboard meeting are not delayed. Everybody on the team should present an overview of the work that needs to be done, the progress made, and the obstacles and challanges they are facing. The teamboard meeting is not a meeting for detailed discussion, but a structured approach for organizing the work in a team. If issues arises and a lengthy and detailed discussion is necessary, an additional meeting is set up.
You are project manager of a large contruction project. A new central warehouse shoud be built for the company. In the middle of execution you discover, that the initial timeline cannot be met. More time is needed in order to complete the project. What is the best course of action?
Explanation:
Reducing the scope (if even possible) affects the satisfaction of the stakeholders in a negative way. Therefore, it is not the best action. Demanding overtime is expensive and not necessary, if other options are available. Before you meet with the senior management you should determine options for schedule compression. This would have the least negative impact on the project.
You are managing a project in a manufacturing company. The project is plan-driven and you used the schedule network analysis to develop the schedule. The project is now in the middle of execution. The CPI for the project is at 0,92 and the SPI is at 0,79. What has probably happened?
Explanation:
Based on the CPI and SPI the project is over budget and behind schedule. A scope change does not necessarily result in cost overruns and delays. An unexpected purchase could explain the cost overrun but not necessarily the delay of the schedule. There is no evidence that an agile approach would have lead to a better project management. It is likely that an activity on the critical path needed more resources and took longer. This explains the cost overruns and the delay.
You are project manager of a small process improvement project, that just got approved and initiated. Now you start the planning of the project. You are approached by a stakeholder, who asks you about the project's budget and the cost baseline. What should you answer?
Explanation:
The project charter shows the initial budget for a project, but does not show any detailed cost estimations (which are part of the cost baseline). Rough estimates are noch detailed enough or create a false impression on the project's estimated costs, so it is not wise to communicate estimates among stakeholders. You can determine a budget without cost estimations, but it is also not wise to do so. To give the stakeholder the information he requested, you need to finish the cost baseline as part of the planning processes.
A project's budget at completion (BAC) is at 200.000€. The team completed 35% of the work and spent 75.000€ on this work packages for the resources to complete those work packages. Evaluate the situation.
Explanation:
Based on the given situation, the project manager cannot assess the progress on the schedule, but she can draw conclusions for the budget. The cost variance is at -5.000€ and the project needs additional funds, which needs to requested via a change request. There is no general rule or indication in the situation, that minor changes do not need to be requested by a change request. Based on the given situation you can only say, that project has overrun its costs by 5.000€ and it needs additional funding.